Hangzhou Customs 100T truck scale project installation

Hangzhou Customs 100T truck scale project installation

 

Confirm that the project is implementable

1. Geological conditionsAssess the geological conditions of the installation site to ensure that the foundation can withstand the weight of the weighbridge and vehicles.

2. Environmental impactConsider environmental factors, such as temperature, humidity, wind, etc., to ensure that the weighbridge can work normally in harsh environments.

3. Approval proceduresIn some areas, the installation of a weighbridge may require approval from the relevant authorities to ensure compliance with local laws and regulations.

Weighbridge is prepared before leaving the factory

1. Installation plan confirmation: Confirm the installation plan and schedule with the person in charge of customs.

2. Strict screening of raw materials to ensure that they meet ISO9001 quality standards, Hengcheng adopts advanced technology and strict design process to ensure stable product performance and high precision.

3.  Carry out multiple tests and verifications to ensure that the products meet customer needs and industry standards.

4. The products are strictly tested before leaving the factory, including accuracy, durability, etc.

Customs on-site preparation

1. The site is leveledThe site where the weighbridge is installed must be flat and solid, and a concrete foundation is usually required to ensure the stability and accuracy of the weighbridge.

2. The size of the venueDepending on the size of the purchased weighbridge, ensure that the site is large enough and allow additional space for vehicles to enter and exit and weigh operations.

3. drainage systemThe site should be well designed with a drainage system to avoid damage to the weighbridge caused by stagnant water.

4. Foundation designAccording to the specifications and load-bearing requirements of the weighbridge, provide basic drawings and design the basic structure that meets the standards.

5. Concrete pouringCarry out concrete foundation construction in accordance with the design drawings to ensure the strength and flatness of the foundation. The concrete needs to be fully cured to meet the strength requirements before the weighbridge can be installed.

6. Embedded parts are installedWhen pouring concrete, it is necessary to pre-embed the installation parts of the weighbridge (such as anchor bolts, sensor bases, etc.) to ensure accurate positioning.

7. Power supplyEnsure that there is a stable power supply near the installation site to meet the power demand of the weighbridge.

8. Signal linesTo transmit the weighing data to the office or monitoring room, the signal line or wireless transmission equipment needs to be arranged in advance.

 

 

 

 

Before installation

1. Weighbridge acceptanceBefore installation, check whether the weighbridge equipment is intact, whether the accessories are complete, and the products have undergone strict testing before leaving the factory, including accuracy, durability, etc.

2. Sensors & GaugesCheck that the load cells and gauges are working properly to ensure that they can be weighed accurately after installation.

3. Professional installation teamThere is a professional installation team for installation to avoid equipment damage or unqualified installation due to improper operation.

4. Tool preparationPrepare the tools and equipment needed for installation, such as cranes, levels, wrenches, etc.

 

 

 

After installation

1. Metrological verificationAfter the installation is completed, it is necessary to contact the local metrology department for verification to ensure that the measurement accuracy of the weighbridge meets the national standard.

2. After-sales serviceAfter-sales service content after installation (e.g. calibration, maintenance, etc.).

 